South PineBack

Completion Date: 17/07/2012

Project Location: Brendale, Brisbane

This project was to provide a 275kV spare system SVC transformer and associated foundation at South Pine substation. The transformer foundation was to be built in place of the existing TX2 transformer foundation and as such the existing foundation needed to be demolished.

The scope of the works included the demolition of the existing TX2 foundation and fire wall, removal of the contaminated material in preparation for the new foundation . the import and compaction of fill, the new transformer foundation to specification, a blast wall between transformers and connection of new foundation to the existing substation oil separation system.